Tokyo 2020; Construction update (July 2018)

Musashino Forest Sport Plaza ©Tokyo Metropolitan Government

 

Venue Scheduled completion date Progress rate
Musashino Forest Sport Plaza March 2017 Completed
Sea Forest Waterway May 2019 42% (On track)
Canoe Slalom Course May 2019 38% (On track)
Dream Island Archery Field June 2019 50% (On track)
Seaside Park Hockey Stadium June 2019 16% (On track)
Olympic Gymnastic Centre October 2019 TBA (On track)
Olympic Stadium November 2019 40% (On track)
Ariake Arena December 2019 21% (On track)
Olympic and Paralympic Village December 2019 40% (On track)
Olympic Aquatics Centre February 2020 35% (On track)

 

Data via the Tokyo Organising Committee of the Olympic and Paralympic Games