International Broadcast Centre Facts & Figures
- Location: PyeongChang Mountain Cluster, Alpensia resort
- Construction Start: December 2015
- IBC Shell Completion: May 2017
- IBC Handover to OBS: 5 June 2017
- Site Area: 122,410.02 sqm
- Gross Floor Area: 51,024.15 sqm
- Functional Space Area
- OBS and RHB broadcast space: Approx. 34,000 sqm
- POCOG & OBS Offices: 5,765,54 sqm
- Common Services: 1,812.04 sqm
Floors
- (Ground floor) RHB compartments, common service area, OBS Offices
- (1st floor) Common service area
- (2nd floor) OBS offices
- (3rd floor) OBS & POCOG offices
- (4th floor) Rooftop TV Studios
Structure
- 6,700 tonnes of steel used in the construction of the IBC
- 616 foundation bearing piles support the structure
Building Size
- Height: 28.55m
- Length: 290m
- Width: 139m
- Parking Lots: 502
- Number of Elevators: Two for people (capacity: 24 people), One for people & cargo (capacity: 38 people)
- Air Handing Units (AHU): If all the AHUs were connected altogether, the total length would be 13.64km
- Bus Ducts: If all the bus ducts were connected altogether, the total length would be 14.5km
- Power : 14400 kVA