CARIOCA ARENA 1/2/3
- Type; New
- Olympic Sports:
- Arena 1: Basketball
- Arena 2: Wrestling (Freestyle and Greco-Roman) + Judo
- Arena 3: Fencing + Taekwondo
- Paralympic Sports;
- Arena 1: Wheelchair Basketball
- Wheelchair Rugby
- Arena 2: Boccia
- Arena 3: Judo
- Legacy; Part of the Olympic Training Centre. Partly reopened in May 2017. (read more)
FUTURE ARENA
- Type; New and temporary
- Olympic Sports; Handball
- Paralympic Sports; Goalball
- Legacy; The Future Arena still has to be removed. Is planned to be re-used in the construction of four schools.
MARIA LENK AQUATICS CENTRE
- Type; Existing
- Olympic Sports; Diving + Synchronised Swimming + Water Polo
- Paralympic Sports ; –
- Legacy; Part of the Olympic Training Centre.
OLYMPIC AQUATICS STADIUM
- Type; New and temporary
- Olympic Sports; Swimming + Water Polo
- Paralympic Sports; Swimming
- Legacy; Only the pools are dismantled. The construction still stands.
OLYMPIC TENNIS CENTRE
- Olympic Sports; Tennis
- Paralympic Sports; Wheelchair Tennis (Centre Court, Court 2-9) / Football 5-a-side (Court 1)
- Legacy; Hosted the FIVB Beach World Tour in May 2017
RIO OLYMPIC ARENA
- Type; Existing
- Olympic Sports; Gymnastics (gala, artistic, rhythmic and trampoline)
- Paralympic Sports; Wheelchair Basketball
- Legacy; Sport and cultural events
RIO OLYMPIC VELODROME
- Type; New and permanent.
- Olympic Sports; Track Cycling
- Paralympic Sports; Para-cycling Track
- Legacy; Part of the Olympic Training Centre. Reopened and hosted the Rio Bike Fest in May 2017. The venue was however damaged by a fire in July 2017. (read more)
RIOCENTRO PAVILION 2/3/4/6
- Type; Existing
- Olympic Sports;
- Pavilion 2: Weightlifting
- Pavilion 3: Table Tennis
- Pavilion 4: Badminton
- Pavilion 6: Boxing
- Paralympic Sports;
- Pavilion 2: Powerlifting
- Pavilion 3: Table Tennis
- Pavilion 4: –
- Pavilion 6: Sitting Volleyball
- Legacy; Exhibition and conventions centre
OLYMPIC GOLF COURSE
- Type; New and permanent
- Olympic Sports; Golf
- Paralympic Sports; –
- Legacy; Uncertain. Maintenance was stopped for a period, users claimed that the ‘green fees’ were to high and there are no big tournaments planned for the future.
BARRA OLYMPIC PARK
- Reopened in January 2017
- Open to the public on weekdays and public holidays.
- New facilities and activities include; the Wall of Champions, multi-sport courts, an outdoor gym, a children’s play area and a skate park.
- Will host Rock in Rio next month.
ATHLETES VILLAGE
- Legacy; Uncertain
- Read more: Rio’s $700 million athletes village was turned into luxury condos but is now reportedly ‘shuttered’ and 93% vacant