Timeline
- Removal of first 14 rows of seating and terraces – August 2013
- Roof dismantling works start – mid-October 2013
- Roof dismantled – by Spring 2014
- New roof erected – by Spring 2015
- Concessions, toilets, turnstiles, hospitality space and rugby pitch complete for use by RWC2015 – by Summer 2015
- RWC2015 matches – September and October 2015
- Retractable seating install, hospitality fit-out, football pitch and athletic track complete – by Summer 2016
- 2016 Diamond League – July 2016
- 2016 Football Season starts – August 2016
- 2017 IPC & IAAF World Athletic Championships